Local Plan Review

Local Plan Review Timetable

This is the timetable for reviewing the Local Plan. It has been updated as a result of the central government changes to the National Planning Policy Framework.  

Timetable for Review

Local Plan Review Starts Early 2024
Call for Sites Spring 2024
Evidence Base Spring 2024
Issues and Options Consultation 20 January - 7 March 2025
Preferred Options Consultation (Reg 18) February 2026
Pre-Submission Consultation (Reg 19) Summer 2026
Submission to Planning Inspectorate November 2026
Review Complete Adoption June 2027

Update October 2025: This timetable has been updated as further work is required on highway modelling for sites and a review of development sites before going out to the Preferred Options (Reg 18) consultation. This proposed revised timetable is due to be formally set out and approved in an updated Local Development Scheme, which will be discussed with members at a Local Plan Sub-Committee in due course.  

More information on this can be found on our news page.  

Local Plan Sub-Committee meetings 

Forthcoming scheduled Local Plan Sub-Committee dates can be found below. Agendas are published 5 working days before each meeting.

Previous meetings:

These meetings considered Policies and sites put forward for development following the call for sites exercise.

The following list gives an indication discussions at each meeting (although not all sites were discussed by area) and includes links to each committee meeting (including agenda and minutes where available):

  • 15 May 2025 (Spatial strategy) 
  • 22 May 2025 (Braintree, Witham) 
  • 28 May 2025 (Halstead, Greenstead Green)
  • 5 June 2025 (Earls Colne, Hatfield Peverel, Kelvedon with Feering, Sible Hedingham)
  • 12 June 2025 (Alphamstone, Ashen, Belchamp Walter, Birdbrook, Black Notley, Bradwell, Bulmer/Bulmer Tye, Bures Hamlet, Castle Hedingham, Colne Engaine, Cressing)
  • 19 June 2025 (Finchingfield, Foxearth, Great Bardfield, Great Maplestead, Great Notley, Great Yeldham, Helions Bumpstead, Lamarsh, Little Maplestead, Ovington, Panfield, Pebmarsh, Pentlow, Rayne, Ridgewell) 
  • 25 June 2025 (The Salings, Shalford, Stambourne, Steeple Bumpstead, Stisted, Sturmer, Toppesfield, Wethersfield, White Colne, White Notley, Wickham St Paul)
  • 24 July 2025 (Gosfield, Rivenhall, Silver End)
  • 31 July 2025 (Coggeshall, Evidence base and policy chapters and other villages with no map changes required)
  • 24 September 2025 - 6:30pm (Large and strategic scale proposals (500+ homes) - Halstead and Northern Area and other associated development - inc Earls Colne, Gosfield, Halstead, Sturmer & Wethersfield).   Additional report including small sites from across the district.
  • 1st October 2025 - 6:30pm (Large and strategic scale proposals (500+ homes) - Braintree and Central Area and other associated development - inc Black Notley, Bocking, Cressing, White Notley, Great Notley, Rayne).
  • 6th October 2025 - 6.30pm (Large and strategic scale proposals (500+ homes) - Witham and Southern Area and other associated development - inc Bradwell, Coggeshall, Hatfield Peverel, Kelvedon, Rivenhall, Silver End).
  • 13th October 2025 - 6.30pm (Policies: Creating Better Places, Transport and Infrastructure)
  • 20th October 2025 - 6.30pm (Additional Housing Policies, The District's Natural Environment, Deferred Sites)

The meetings are streamed live on YouTube. You can also sign up to our planning newsletter to be the first to hear of latest updates relating to the Local Plan Review.

Page updated: 27 October 2025

Planning Policy

Address: Causeway House
Bocking End
Braintree
Essex
CM7 9HB

Telephone: 01376 552525

email envelope icon and mobile phone icon

Subscribe to our planning email updates

Receive the latest information and updates on our planning services and how you can help shape policies, delivered directly straight to your inbox.

Sign up today