If you intend to build or alter a premises that will be used for
regulated activities, provided that you are aged 18 or over
and have an interest in the premises you can apply for a
provisional statement.
Whilst you will need to complete a different
application form and must
provide a schedule of works and plans, the rest of the
requirements, application procedure and decision making are
the same as if you are applying for a new licence.
What do I do when the work is finished ?
You will need to apply for a premises licence. Provided nothing
substantial has changed representations will not be accepted if the
person could reasonably have been expected to make such an
objection at the time the Provisional Statement was applied for and
there has been no material change in circumstances of the premises
or the vicinity of them.